Sustainable performance of just-in-time (JIT) management in time-dependent batch delivery scheduling of precast construction

Journal of Cleaner Production - Tập 193 - Trang 684-701 - 2018
Liulin Kong1, Heng Li2, Hanbin Luo3, Lieyun Ding4, Xiaoling Zhang5
1School of Civil Engineering & Mechanics, Huazhong University of Science & Technology, Department of Building and Real Estate, The Hong Kong Polytechnic University, Hong Kong, China
2Department of Building and Real Estate, The Hong Kong Polytechnic University, Hong Kong, China
3School of Civil Engineering & Mechanics, Huazhong University of Science & Technology, China
4Institution of Construction Engineering, Huazhong University of Science & Technology, China
5Department of Public Policy, City University of Hong Kong, Shenzhen Research Institute, City University of Hong Kong, Shenzhen, China

Tài liệu tham khảo

Akintoye, 1995, Just-in-Time application and implementation for building material management, Construct. Manag. Econ., 13, 105, 10.1080/01446199500000013

Anvari, 2016, A multi-objective GA-based optimisation for holistic Manufacturing, transportation and Assembly of precast construction, Autom. ConStruct., 71, 226, 10.1016/j.autcon.2016.08.007

Arashpour, 2016, Off-site construction optimization: sequencing multiple job classes with time constraints, Autom. ConStruct., 71, 262, 10.1016/j.autcon.2016.08.001

Arashpour, 2016, Off-site construction optimization: sequencing multiple job classes with time constraints, Autom. ConStruct., 71, 262, 10.1016/j.autcon.2016.08.001

Chan, 2001, An application of genetic algorithms to precast production scheduling, Comput. Struct., 79, 1605, 10.1016/S0045-7949(01)00036-0

Chan, 2002, Constraint programming approach to precast production scheduling, J. Construct. Eng. Manag., 128, 513, 10.1061/(ASCE)0733-9364(2002)128:6(513)

Cheng, 2002, Integrating barcode and GIS for monitoring construction progress, Autom. ConStruct., 11, 23, 10.1016/S0926-5805(01)00043-7

Cheng, 1994, Batch delivery scheduling on a single-machine, J. Oper. Res. Soc., 45, 1211, 10.1057/jors.1994.191

Christian, 1995, Effects of delay times on production rates in construction, J. Construct. Eng. Manag., 121, 20, 10.1061/(ASCE)0733-9364(1995)121:1(20)

Dabia, 2013, Branch and price for the time-dependent vehicle routing problem with time windows, Transport. Sci., 47, 380, 10.1287/trsc.1120.0445

Hall, 2003, Supply chain scheduling: batching and delivery, Oper. Res., 51, 566, 10.1287/opre.51.4.566.16106

Han, 2014, A robust scenario approach for the vehicle routing problem with uncertain travel times, Transport. Sci., 48, 373, 10.1287/trsc.2013.0476

Hu, 2007, A study of resource planning for precast production, Architect. Sci. Rev., 50, 106, 10.3763/asre.2007.5016

Ip, 2000, Multi-product planning and scheduling using genetic algorithm approach, Comput. Ind. Eng., 38, 283, 10.1016/S0360-8352(00)00044-9

Jaillon, 2008, Sustainable construction aspects of using prefabrication in dense urban environment: a Hong Kong case study, Construct. Manag. Econ., 26, 953, 10.1080/01446190802259043

Khalili, 2013, Integrated prefabrication configuration and component grouping for resource optimization of precast production, J. Construct. Eng. Manag., 140, 04013052, 10.1061/(ASCE)CO.1943-7862.0000798

Ko, 2010, An integrated framework for reducing precast fabrication inventory, J. Civ. Eng. Manag., 16, 418

Leu, 2002, GA-based resource-constrained flow-shop scheduling model for mixed precast production, Autom. ConStruct., 11, 439, 10.1016/S0926-5805(01)00083-8

Li, 2014, Critical review of the research on the management of prefabricated construction, Habitat Int., 43, 240, 10.1016/j.habitatint.2014.04.001

Liu, 2014, Sustainable performance oriented operational decision-making of single machine systems with deterministic product arrival time, J. Clean. Prod., 85, 318, 10.1016/j.jclepro.2014.07.025

Lu, 2013, Investigating waste reduction potential in the upstream processes of offshore prefabrication construction, Renew. Sustain. Energy Rev., 28, 804, 10.1016/j.rser.2013.08.048

Malandraki, 1992, Time dependent vehicle routing problems: formulations, properties and heuristic algorithms, Transport. Sci., 26, 185, 10.1287/trsc.26.3.185

Mason, 1991, Minimizing flow time on a single machine with job classes and setup times, Nav. Res. Logist., 38, 333, 10.1002/1520-6750(199106)38:3<333::AID-NAV3220380305>3.0.CO;2-0

Mazdeh, 2007, A branch-and-bound algorithm for single-machine scheduling with batch delivery minimizing flow times and delivery costs, Eur. J. Oper. Res., 183, 74, 10.1016/j.ejor.2006.09.087

Min, 2006, EOQ, JIT and fixed costs in the ready-mixed concrete industry, Int. J. Prod. Econ., 102, 167, 10.1016/j.ijpe.2005.03.002

Mouzon, 2008, A framework to minimise total energy consumption and total tardiness on a single machine, International Journal of Sustainable Engineering, 1, 105, 10.1080/19397030802257236

Ng, 2009, Enhancing the logistics of construction materials through activity-based simulation approach. Engineering, Construction and Architectural Management, 16, 224, 10.1108/09699980910951645

Ocheoha, 2013, 1455

Oliveira, 2004, A multiple objective model to deal with economy–energy–environment interactions, Eur. J. Oper. Res., 153, 370, 10.1016/S0377-2217(03)00159-0

Pheng, 2001, Just-in-Time management of precast concrete components, J. Construct. Eng. Manag., 127, 494, 10.1061/(ASCE)0733-9364(2001)127:6(494)

Pheng, 1999, The application of JIT philosophy to construction: a case study in site layout, Construct. Manag. Econ., 17, 657, 10.1080/014461999371268

Pheng, 2012, 261

Polat, 2008, Factors affecting the use of precast concrete systems in the United States, J. Construct. Eng. Manag., 134, 169, 10.1061/(ASCE)0733-9364(2008)134:3(169)

Potts, 2000, Scheduling with batching: a review, Eur. J. Oper. Res., 120, 228, 10.1016/S0377-2217(99)00153-8

Sarkis, 2003, A strategic decision framework for green supply chain management, J. Clean. Prod., 11, 397, 10.1016/S0959-6526(02)00062-8

Shabtay, 2010, Scheduling and due date assignment to minimize earliness, tardiness, holding, due date assignment and batch delivery costs, Int. J. Prod. Econ., 123, 235, 10.1016/j.ijpe.2009.08.012

Viana, 2015, Analysis of HVAC subcontractor mechanisms for JIT material supply to a construction site, 28

Wong, 2003

Yee, 2001

Yin, 2013, Single-machine batch delivery scheduling with an assignable common due date and controllable processing times, Comput. Ind. Eng., 65, 652, 10.1016/j.cie.2013.05.003

Yin, 2013, Single-machine batch delivery scheduling with an assignable common due window, Omega, 41, 216, 10.1016/j.omega.2012.06.002

Zhao, 2017, An optimization model for green supply chain management by using a big data analytic approach, J. Clean. Prod., 142, 1085, 10.1016/j.jclepro.2016.03.006