Multi‐project cash flow optimization: non‐inferior solution through neuro‐multiobjective algorithm

Emerald - 2001
K.C.LAM1, TIESONGHU2, S.O.CHEUNG1, R.K.K.YUEN1, Z.M.DENG1
1Department of Building and Construction, City University of Hong Kong
2Department of Building and Construction, City University of Hong Kong, Department of Hydraulic Engineering, Wuhan University, China

Tóm tắt

Modelling of the multiproject cash flow decisions in a contracting firm facilitates optimal resource utilization, financial planning, profit forecasting and enables the inclusion of cash‐flow liquidity in forecasting. However, a great challenge for contracting firm to manage his multiproject cash flow when large and multiple construction projects are involved (manipulate large amount of resources, e.g. labour, plant, material, cost, etc.). In such cases, the complexity of the problem, hence the constraints involved, renders most existing regular optimization techniques computationally intractable within reasonable time frames. This limit inhibits the ability of contracting firms to complete construction projects at maximum efficiency through efficient utilization of resources among projects. Recently, artificial neural networks have demonstrated its strength in solving many optimization problems efficiently. In this regard a novel recurrent‐neural‐network model that integrates multi‐objective linear programming and neural network (MOLPNN) techniques has been developed. The model was applied to a relatively large contracting company running 10 projects concurrently in Hong Kong. The case study verified the feasibility and applicability of the MOLPNN to the defined problem. A comparison undertaken of two optimal schedules (i.e. risk‐avoiding scheme A and risk‐seeking scheme B) of cash flow based on the decision maker's preference is described in this paper.

Từ khóa


Tài liệu tham khảo

10.1109/72.363481

Avriel A., 1976, Nonlinear Programming Analysis and Methods

10.1108/eb021106

10.1080/014461996373296

10.1061/(ASCE)0733-9364(1995)121:1(130)

10.1061/(ASCE)0733-9364(1997)123:3(214)

Clough R.H., 1991, Construction Project Management, 3

Flood I., Proceedings of the 6th International Symposium on Automation and Robotics in Construction, 204

10.1109/72.737495

10.1108/eb021080

10.1061/(ASCE)0887-3801(1994)8:1(72)

Hiller F.S., 1990, Introduction to Mathematical Programming

Hopfield J.J., 1985, Biological Cybernetics, 52, 141, 10.1007/BF00339943

Hu T ., 1998, Acta Electronica Sinica, 26, 106

Hu T ., 1997, Neural Prediction and Optimization

Hu T., 1996, Pattern Recognition and Artificial Intelligence, 5, 89

10.1061/(ASCE)0887-3801(1992)6:2(178)

10.1080/09613219408727411

Lam, K.C. (1997) The Optimization of Financial Decisions in a Contracting Firm. PhD Thesis,The University of New South Wales, Sydney.

10.1080/014461999371204

Lam K.C., 2000, Journal of Engineering, Construction and Architectural Management, in press.

Lam K.C., 2000, Construction Management and Economics,in press

10.1108/eb021023

Li H., 1998, Journal of Construction Engineering and Management, 124, 123

10.1061/(ASCE)0733-9364(1999)125:3(185)

10.1061/(ASCE)0733-9364(1991)117:4(606)

10.1139/l93-007

10.1061/(ASCE)0887-3801(1994)8:2(221)

10.1109/72.105413

10.1016/0893-6080(91)90033-2

10.1109/59.761910

10.1109/72.728383

10.1109/59.667341

10.1109/82.160169

10.1016/0375-9601(90)90136-C

Hu T., 1998, Acta Electronica Sinica, 26, 106

Kennedy M.P., 1988, IEEE Transactions on Neural Networks, 35, 554

10.1109/31.52732