Major causes of problems between contractors and subcontractors in the Gaza Strip

Journal of Financial Management of Property and Construction - Tập 17 Số 1 - Trang 92-112 - 2012
AdnanEnshassi1, FaisalArain2, BassamTayeh3
1Department of Civil Engineering, Islamic University of Gaza, Gaza, Palestine
2School of Construction, Southern Alberta Institute of Technology, Calgary, Canada
3School of Civil Engineering, Universiti Sains Malaysia, Penang, Malaysia

Tóm tắt

PurposeSubcontractors play a significant role in the Palestinian construction industry as about 90 per cent of the work is performed by subcontractors. The main objective of this paper is to identify and analyse the major problems which exist between the contractors and subcontractors in the construction industry in the Gaza Strip.Design/methodology/approachA questionnaire was designed to elicit contractors' and subcontractors' viewpoints regarding the most important causes of problems that affect the relationship between them. A total of 53 problems were identified based on a literature review, a pilot study was considered in this study and was listed under five groups. A total of 150 questionnaires were randomly sent to contractors and subcontractors. The respondents had extensive experience in the construction industry with average working experience of 20 years. The questionnaire was validated by the criterion‐related reliability test that measures the correlation coefficients between the factors selected for in each group and for all groups as one entity, and structure validity test (Spearman test).FindingsThe result of the survey indicated that, assigning part of the works to new subcontractor without informing the original subcontractor, contractor's financial problems, delay in contract progress payments, non‐adherence to the conditions of the contract, non‐adherence of the subcontractor to the time schedule, and lack of construction quality work were the most important causes of interface problems, while involvement in several projects with the contractor at the same time, weather conditions, and geological problems on site were considered as trivial causes of potential interface problems. Spearman's rank correlation tests showed that there are no differences in the viewpoints between contractors and subcontractors.Originality/valueThe research findings might assist practitioners to focus on major problems which have existed between the contractors and subcontractors in the construction industry in their present and future projects. By eliminating or minimizing these problems, subcontractors are encouraged to contribute significantly to the capital risk, resources, managerial effort, and business expertise supporting the largest industry in Palestine. The paper would be valuable for all academics and industry professionals involved in construction business in general.

Từ khóa


Tài liệu tham khảo

Al‐Hammad, A. (1993), “Factors affecting the relationship between contractors and their subcontractors in Saudi Arabia”, Building Research and Information, Vol. 21 No. 5, pp. 269‐73.

Al‐Hammad, A. and Assaf, S. (1992), “Design construction interface problems in Saudi Arabia”, Building Research and Information, Vol. 20 No. 1, pp. 60‐3.

Al‐Hazmi, M. (1987), “Causes of delay in large building construction projects”, available at: http://goliath.ecnext.com (accessed 1 November 2010).

Alinaitwe, H.M., Mwakali, J.A. and Hansson, B. (2007), “Factors affecting the productivity of building craftsmen studies of Uganda”, Journal of Civil Engineering and Management, Vol. 13 No. 3, pp. 169‐76.

Arditi, D. and Chotibhongs, R. (2005), “Issues in subcontracting practice”, Journal of Construction Engineering and Management, Vol. 131 No. 8, pp. 866‐78, (ASCE).

Chung, W.F., Skitmore, M. and Ng, S.T. (2003), “Ten basic factors to identify suitable subcontractors for construction projects”, paper presented at CIB TG 23 International Conference.

Enshassi, A. and Medoukh, Z. (2007), “The contractor‐subcontractor relationship: the general contractor's view”, Proceedings of the International Conference in Building Education and Research (BEAR 2008), Sri Lanka, February 2008, pp. 1520‐7.

Enshassi, A., Choudhry, R.M., Mayer, P.E. and Shoman, Y. (2008), “Safety performance of subcontractors in the Palestinian construction industry”, Journal of Construction in Developing Countries, Vol. 13 No. 1, pp. 51‐62.

Enshassi, A., Mohamed, S., Abu Mustafa, Z. and Mayer, P.E. (2007), “Factors affecting labour productivity in building projects in the Gaza strip”, Journal of Civil Engineering and Management, Vol. 13 No. 4, pp. 245‐54.

Fah, C. (2006), “A study on domestic subcontractor”, available at: www.efka.utm (accessed 1 November 2010).

Fellows, R. and Liu, A. (1997), Research Methods for Construction, Blackwell, Oxford.

Hinze, J. and Tracy, A. (1994), “The contractor‐subcontractor relationship: the subcontractor's view”, Journal of Construction Engineering and Management, Vol. 120 No. 2, pp. 274‐87, (ASCE).

Huang, R.Y., Huang, C.T., Lin, H. and Ku, W.H. (2008), “Factor analysis of interface problems among construction parties a case study of MRT”, Journal of Marine Science and Technology, Vol. 16 No. 1, pp. 52‐63.

Israel, G.D. (2003), Determining Sample Size, Department of Agriculture, Institution of food and agricultural science, University of Florida, Gainesville, FL.

Khle, S. and Arditi, D. (2001), “General contractors' relationships with subcontractors: a strategic asset”, Construction Management and Economics, Vol. 19, pp. 541‐9.

Kish, L. (1965), Survey Sampling, Wiley, New York, NY.

Kumaraswamy, M.M. and Matthews, J.D. (2000), “Improved subcontractor selection employing partnering principles”, Journal of Construction Engineering and Management, Vol. 16 No. 3, pp. 47‐57 (ASCE).

Moore, C., Mosley, D. and Slagle, M. (1992), “Partnering guidelines fir win‐win project management”, Project Management Journal, Vol. 22 No. 1, pp. 18‐21.

Moser, C.A. and Kalton, G. (1971), Survey Methods in Social Investigation, Heinemann Education, London.

Ng, S.T., Luu, C.D.T. and Chu, A.W.K. (2008), “Delineating criteria for subcontractors registration considering divergence in skill base and scales”, International. Journal of Project Management, Vol. 26, pp. 448‐56.

Othman, M.R. (2007), Forging Main and Subcontractor Relationship for Successful Projects, available at: http://rakan1.jkr.gov.my/csfj/editor/files/File/Projek/LessonsLearned/MAINandSUB_2.pdf (accessed 1 November 2010).

Palestinian Contractors Union (2008), PCU, Gaza.

PCICB (2003), Guidelines on Subcontracting Practice, Provisional Construction Industry Coordination Board, available at: www.pcicb.gov.hk (accessed 1 November 2010).

Proctor, J.R. Jr (1996), “Golden rule of contractor‐subcontractor relations”, Practice Periodical on Structural Design and Construction, Vol. 1 No. 1, pp. 12‐14.

Sambasivan, M. and Soon, Y.W. (2007), “Causes and effects of delays in Malaysian construction industry”, International Journal of Project Management, Vol. 25, pp. 517‐26.

Arain, F.M., Assaf, S. and Low, S.P. (2004), “Causes of discrepancies between design and construction”, Architectural Science Review, Vol. 47 No. 3, pp. 237‐49.