Dismantling Quantity Estimation for Nuclear Power Plant: Scan-to-BIM versus Conventional Method
KSCE Journal of Civil Engineering - Trang 1-15 - 2024
Tóm tắt
This paper presents a case study of using Scan-to-BIM technology for evaluating the quantity and cost of a nuclear power plant during the decommissioning process. The study proposes a process for applying Scan-to-BIM in the dismantling stage and develops a BIM-based VPL (Visual Programming Language) to acquire accurate as-is databases that are crucial for nuclear power plants handling radioactive materials. The proposed process and system were applied to K-1 NPP (Nuclear Power Plant), the first nuclear power plant in Korea, and the results were compared to those obtained using the conventional method. The study found that errors in quantity evaluation using the conventional method ranged from around 10% to over 10 times, and were attributed to various causes such as outdated as-is drawings and limitations in expressing information in drawings. By using the Scan-to-BIM process and system, errors in quantity evaluation were significantly reduced, and the conventional method was found to have underestimated the dismantling cost by 20%. The findings of this study provide important insights for the efficient and accurate decommissioning of nuclear power plants, and demonstrate the effectiveness of the proposed method and system for evaluating the quantity and cost of a nuclear power plant during the decommissioning process.
Tài liệu tham khảo
Abanda FH, Vidalakis C, Oti AH, Tah JHM (2015) A critical analysis of building information modelling systems used in construction projects. Advances in Engineering Software 90:183–201, DOI: https://doi.org/10.1016/j.advengsoft.2015.08.009
AIA (2022) AIA Document E202-2022. American Institute of Architects Retrieved December 27, 2023, https://aiacontracts.com/
Akinade OO, Oyedele LO (2019) Integrating construction supply chains within a circular economy: An ANFIS-based waste analytics system (A-WAS). Journal of Cleaner Production 299(20):863–873, DOI: https://doi.org/10.1016/j.jclepro.2019.04.232
André N, Luna OS, Annelise NS, Brunno PB, Hugo DH, Charles JO (2021) BIM plug-in technology for construction waste quantification. Revista Brasileira de Gestão Ambiental e Sustentabilidade 8(20): 1605–1619, DOI: https://doi.org/10.21438/rbgas(2021)082021
Ashokkumar V, Varghese S (2018) BIM-based 3D model for construction waste quantification. International Research Journal of Engineering and Technology (IRJET) 5(5):3069–3076
Beatriz CG, Amal B, Fernanda L, Kasey MF (2019) BIM-based automated construction waste estimation algorithms: The case of concrete and drywall waste streams. Waste Management 8:825–832, DOI: https://doi.org/10.1016/j.wasman.2019.03.010
Bedrick J, Ikerd W, Reinhardt, J (2021) Level of development (LOD) specification. BIM Forum Retrieved December 27, 2023, https://bimforum.org/resource/lod-level-of-development-lod-specification/
Charles RQ, Hao S, Kaichun M, Leonidas JG (2017) PointNet: Deep Learning on point sets for 3D Classification and Segmentation. 2017 IEEE Conference on Computer Vision and Pattern Recognition (CVPR) Honolulu, HI, USA, DOI: https://doi.org/10.1109/CVPR.2017.16
Cheng JCP, Ma LYH (2013) A BIM-based system for demolition and renovation waste estimation and planning. Waste Management 33(6): 1539–1551, DOI: https://doi.org/10.1016/j.wasman.2013.01.001
Colucci E, Iacono E, Matrone F, Ventura GM (2022) A BIM-GIS Integrated database to support planned maintenance activities of historical built heritage. Communications in Computer and Information Science 1507, DOI: https://doi.org/10.1007/978-3-030-94426-1_14
Ding Z, Liu S, Liao L, Zhang L (2019) A digital construction framework integrating building information modeling and reverse engineering technologies for renovation projects. Automation in Construction 102:45–58, DOI: https://doi.org/10.1016/j.autcon.2019.02.012
EPRI (2005) Maine yankee decommissioning experience report. Report No.1011734, Electric Power Research Institute, Palo Alto, CA, USA
Ge XJ, Livesey P, Wang J, Huang SD, He X, Zhang CQ (2017) Deconstruction waste management through 3d reconstruction and BIM: A case study. Visualization in Engineering 5(1), DOI: https://doi.org/10.1186/s40327-017-0050-5
Ghannad P, Lee YC, Dimyadi J, Solihin W (2019) Automated BIM data validation integrating open-standard schema with visual programming language. Advanced Engineering Informatics 40:14–28, DOI: https://doi.org/10.1016/j.aei.2019.01.006
Ham N, Lee SH (2018) Empirical study on structural safety diagnosis of large-scale civil infrastructure using laser scanning and BIM. Sustainability 10(11):4024, DOI: https://doi.org/10.3390/su10114024
IAEA (2008) Managing low radioactivity material from the decommissioning of nuclear facilities. Technical Report Series No.462, International Atomic Energy Agency, Vienna, Austria
IAEA (2018) Decommissioning of nuclear power plants, research reactors and other nuclear fuel cycle facilities. Specific Safety Guide No. SSG-47, International Atomic Energy Agency, Vienna, Austria
IAEA (2022) PRIS database. International Atomic Energy Agency Retrieved December 27, 2023, https://pris.iaea.org/pris/home.aspx
Jeong HJ, Ham NH, Lee BD, Park KM, Kim JJ (2019) A study on the improvement of re-pair and reinforcement quantity take-off in fire-damaged area using 3D laser scanning. Journal of KIBIM 9(1):11–21, DOI: https://doi.org/10.13161/KIBIM.2019.9.1.011
Jeong KS, Lee DG, Lee KW, Oh WZ (2004) Study on the state-of-the-arts approaches and methodologies for the decommissioning cost estimation of nuclear facilities. KAERI/AR-707/2004, Korea Atomic Energy Research Institute, Daejeon, Korea
KAERI (2018) Nuclear decommissioning industry enhancement project. Nuclear Policy Brief Report 2018-5, Korea Atomic Energy Research Institute, Daejeon, Korea
Kai K, Svetlana B, Yaqi D, Ray YZ (2022) Building demolition waste management through smart BIM: A case study in Hong Kong. Waste Management 143:69–83, DOI: https://doi.org/10.1016/j.wasman.2022.02.027
Kensek K (2015) Visual programming for building information modeling: Energy and shading analysis case studies. Journal of Green Building 10(4):28–43, DOI: https://doi.org/10.3992/jgb.10.4.28
Kim D, Kwak Y, Sohn H (2020) Accelerated cable-stayed bridge construction using terrestrial laser scanning. Automation in Construction 117:103269, DOI: https://doi.org/10.1016/j.autcon.2020.103269
Kim H, Park J (2011) Development of computer program for estimating decommissioning cost. Proceedings of the ASME 2011 14th International Conference on Environmental Remediation and Radioactive Waste Management, September 25–29, Reims, France
Kim T, Yoon Y, Lee B, Ham N, Kim J (2022) Cost–Benefit analysis of scan-vs-BIM-based quality management. Buildings 12(12):2052, DOI: https://doi.org/10.3390/buildings12122052
Kim TH, Woo W, Chung K (2019) 3D Scanning data coordination and As-Built-BIM construction process optimization. Architectural Research 21(4):111–116, DOI: https://doi.org/10.5659/AIKAR.2019.21.4.111
Kim YC, Hong WH, Park JW, Cha GW (2017) An estimation framework for building information modeling (BIM)-based demolition waste by type. Waste Management & Research 35(12):1285–1295, DOI: https://doi.org/10.1177/0734242X17736381
KNSSC (2014) Regulations on classification and self-disposal criteria of radioactive waste. Notification No. 2014-3, Korea Nuclear Safety and Security Commission, Seoul, Korea
KNSSC (2015) Regulations on the preparation of decom-missioning plans for nuclear facilities. Notification No. 2015-8, Korea Nuclear Safety and Security Commission, Seoul, Korea
KORAD (2017) Implementation plan for low and intermediate-level radioactive waste management. Korea Radioactive Waste Agency, Korea
Kossakowski PG (2023) Visual programming as modern and effective structural design technology analysis of opportunities, challenges, and future developments based on the use of dynamo. Applied Sciences 13(16):9298, DOI: https://doi.org/10.3390/app13169298
Lee DS, Kim GH (2020) Smart quality inspection scheme for construction project using 3D scanning technology. Journal of the Korea Institute of Building Construction 20(2):191–198, DOI: https://doi.org/10.5345/JKIBC.2020.20.2.191
Lorz J, Han B (2013) Technical studies and analysis of condensate polishing plant (CPP) in power plant. Proceedings of the Korean Society of Plant Engineers Conference, June 20, Seoul, Korea
Marzouk M, El-Bendary N (2022) Facility management of gas turbine power plants using 3D laser scanning. HBRC Journal 18(1):73–83, DOI: https://doi.org/10.1080/16874048.2022.2026013
MOTIE (2019) Regulations on calculation standards for radioactive waste management costs and spent nuclear fuel management charges. Announcement No. 2019-17, Ministry of Trade, Industry and Energy, Korea
Niu J, Ding Z (2021) A BIM Based digital framework for hotel renovation projects: An Integrated application of 3D scanning and prefabrication technology. Proceedings of the 24th International Symposium on Advancement of Construction Management and Real Estate June 08, Singapore, DOI: https://doi.org/10.1007/978-981-15-8892-1_78
Park T, Han B, Park K (2019) SACER: A computer program for decommissioning schedule analysis and cost estimate of nuclear power plants. Proceedings of the Korean Radioactive Waste Society Conference, May 8–10, Busan, Korea
Park JJ, Shin JC, Hwang JW, Lee KH, Seo HJ, Lee IM (2012) Assessment of over/under-break of tunnel utilizing BIM and 3D laser scanner. Journal of Korean Tunnelling and Underground Space Association 14(4):437–451, DOI: https://doi.org/10.9711/KTAJ.2012.14.4.437
PNNL (1994) Estimating boiling water reactor decommissioning costs: A user’s manual for the BWR Cost estimating computer program (CECP) software. PNL-10086 Pacific Northwest National Laboratory, Washington DC, USA
PPS (2022) Standard unit price of Korean public procurement service, Public Procurement Service, Korea
Quiñones R, Llatas C, Montes MV, Cortés I (2022) Quantification of construction waste in early design stages using BIM-based tool. Recycling 7(5):63, DOI: https://doi.org/10.3390/recycling7050063
Randall T (2011) Construction engineering requirements for integrating laser scanning technology and building information modeling. Journal of Construction Engineering and Management 137(10):867–875, DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000322
Rocha G, Mateus L, Fernández J, Ferreira V (2020) A scan-to-BIM methodology applied to heritage buildings. Heritage 3(1):47–67, DOI: https://doi.org/10.3390/heritage3010004
Russa FM, Santagati C (2021) An AI-based DSS for preventive conservation of museum collections in historic buildings. Journal of Archaeological Science 35:102735, DOI: https://doi.org/10.1016/j.jasrep.2020.102735
Seoul Metropolitan Government (2022) Standard unit price explanation for electrical work, Retrieved December 27, 2023, https://news.seoul.go.kr/gov/archives/539565
Shin J (2019) Development of AAB (Algorithm-Aided BIM) Based 3D design bases management system in nuclear power plant. Korean Journal of Construction Engineering and Management 20(2):28–36, DOI: https://doi.org/10.6106/KJCEM.2019.20.2.028
Shu S, Shimeng L, Jingyi J, Qian W, Zhao X (2021) A building information modeling-based tool for estimating building demolition waste and evaluating its environmental impacts. Waste Management 134:159–169, DOI: https://doi.org/10.1016/j.wasman.2021.07.025
Staiger R (2011) 10 years of terrestrial laser scanning technology. Systems and Applications
Turco M, Giovannini EC, Tomalini A (2022) Parametric and visual programming BIM applied to museums, linking container and content. ISPRS International Journal of Geo-Information 11(7):411, DOI: https://doi.org/10.3390/ijgi11070411
U.S. NRC (2014) Standard format and content for post-shutdown decommissioning activities report. Regulatory Guide 1.185, U.S. Nuclear Regulatory Commission, Washington DC, USA
U.S. NRC (2023) Decommissioning process. U.S. Nuclear Regulatory Commission, Retrieved December 27, 2023, https://www.nrc.gov/waste/decommissioning/process.html
United-BIM (2023) Case Study–Point Cloud Scan to BIM Modeling for Mechanical Room, Retrieved December 27, 2023, https://www.united-bim.com/portfolio/point-cloud-scan-to-bim-case-study/
Ursini A, Grazzini A, Matrone F, Zerbinatti M (2022) From scan-to-BIM to a structural finite elements model of built heritage for dynamic simulation. Automation in Construction 142:104518, DOI: https://doi.org/10.1016/j.autcon.2022.104518
VMTS (2023) 3D Laser Scanning and creating BWTS Installation drawings in Vietnam, Retrieved December 27, 2023, https://vmts.ch/en/portfolio/3dlaserscanning-bwts-retrofit-installation/
Wu C, Yuan Y, Tang Y, Tian B (2022) Application of terrestrial laser scanning (TLS) in the Architecture, Engineering and Construction (AEC) Industry. Sensors 22(1):265, DOI: https://doi.org/10.3390/s22010265
Xu J, Shi Yi, Xie Y, Zhao S (2019) A BIM-Based construction and demolition waste information management system for greenhouse gas quantification and reduction. Journal of Cleaner Production 229(20):308–324, DOI: https://doi.org/10.1016/j.jclepro.2019.04.158